TWIN NATURAL GAS COMPRESSION PLANTS:
─ Location: Furrial and Punta de Mata
─ Twin Natural Gas Compression Plants Turn-key Project for Gas-Lift production.
─ 320 MMSCFD capacity.
─ 8x 3612 Caterpillar Gas Engines (29,100 HP) with Ariel compressors.
─ Elevating 1,200 PSIG to 4,500 PSIG.
─ Commissioning and start-up assistance with our experienced personnel.
─ Six (6) months O&M contract.


PCO GAS COMPRESSION PLANT
─ 25 MMSCFD total capacity.
─ Elevating pressure to 1,200 PSIG for pipeline transmission.
─ Including gas sweetening and dehydration facilities.
─ 4x 3608 Caterpillar gas engines (7,200 HP) with Ariel compressors.
ON SITE WORKSHOP SAUDI ARABIA. DESIGN &CONSTRUCTION
─ 3-bay workshop design for the maintenance of heavy machinery and equipment.
─ 4 containers of 40 feet with a crane bridge on top of a 5 tons capacity.


POWER PLANTS
─ Morropo Power Station, 33,6e MVA
─ Venetur Location, 12,8e MVA
─ Guafita Generator Station, 11,2e MVA
─ El Baul Power Station, 10,5e MVA
─ Proarepa Power Station, 4,92e MVA
─ Bailadores Power Station, 1,64e MVA
OIL FIELD 6.8 MW POWER PLANT
─ Location: Suriname.
─ Modern Packaged Power Station (PPS), with a 6.8 MW total installed capacity.
─ 4x 1.71 MW (HHI 9h21/32) power generating sets, Crude Oil / HFO.


MOENGO 11MW
– Location: Suriname.
– Highest Efficiency Rating for Dual Reciprocating Engines.
– Natural gas or crude oil.
– 5x containerized generating sets.
– Total capacity of 11 MW Dual fuel and 11 MW solar energy with PV.
REMOTE SOLUTIONS WITH PV POWER
– Off-grid, containerized photovoltaic power generation system with a plug-and-play capability.
– Complete with BESS and Inverters.
– PV capacities of 25 kWp in a 20 ft container, or 84 kWp in a 40 ft container.
– Ideal solution for remote oil well pumps, water pumping, and off-grid utility.


PORTABLE POWER GENERATION WITH LPG TURBINES
─Small turbine technology application
─Reduced site emissions.
─Modular units from 333 kW to 1.3 MW.
─Fuel: LPG (Liquefied Petroleum Gas).
GAS EXPLORATION & PRODUCTION OPERATION
─Productive assets in Alworth Field, Zapata, Texas.
─The gross area of 3,360.84 acres.
─18 wells (14 in Zapata County, 4 wells in Jim Hogg County).
─Average 1.8 MMSCFD.


PETROSUCRE, COROCORO PROJECT CPF
─Service description: preventive and corrective maintenance to gas lift (1300 PSI) and gas injection (3000 PSI) compression packages installed in the central production plant 4F, Corocoro oil field.
─Location: Paria’s gulf, Corocoro oilfield.
─Equipment: 02 compressor packages G3616 4300 HP each, 02 compressor packages G3606 2800 HP each.
CARDON IV, PERLA NAT GAS PRODUCTION PLATFORM
─Corrective and predictive maintenance activities under on-call mode, for power generators, switchgears, MCC and boards, in the offshore pp1 platform.
─Equipment: an electrical system of two marathon magnamax gas-fired generators, 100 kW each and a 100 kW diesel backup power generator


CARDON IV, TIGUADARE ONSHORE NAT GAS FACILITY
─Corrective and predictive maintenance activities under on-call mode, for electric generation system in onshore facilities
─Equipment: 02 NAT gas power generators of 740 KW each, and a backup and a diesel power generator of 725 kW at 480 volts and 60 HZ
GTE 300MW COMBINED CYCLE AND NGL FACILITY
─Construction status: civil phase; soil remediation completed.
─Investment: $759 million.
─Location: West Bank Demerara, Guyana.
─Turnkey Project: 300 MW power plant and NGL facility for 50 MMSCF of natural gas, complete with a 60 MWh BESS system and a 230 kV substation.
─Contract Execution: 12 December 2022.
─COD: Q3 2025.
─Soil remediation completed.
─Compacted terrace: more than 1.3 Million cubic meters of sand
─Installed more 300,000 wick drains.



PUERTO RICO SANTA ISABEL PHOTOVOLTAIC PLANT
─Status: Puerto Rico Energy Bureau Tranche 2 Bidding Process.
─Business Model: PPOA (25-year term).
─30 MWac photovoltaic plant, with potential to expand to 62 MWac.
─BESS for ramp and frequency control.
─Land currently under Purchase Option.
PUERTO RICO 300MW COMBINED CYCLE TO H2 PPOA
─Status: P3A Bidding Process.
─Business Model: PPOA (30-year term).
─300 MW CCTG Siemens configuration 2 x (2+1) (SGT-800 Gas Turbine) SST-400 (Steam Turbine).
─Multiple Fuels: Natural Gas and Hydrogen (Diesel backup).
─Annual Availability Factor: 95%.
─Land currently under Purchase Option.
